Hackspace Construction Work

As you will be aware the space is closed during Lockdown however we have kept it open for anyone wanting to do work on the space as it can be classed as construction site

Below is a list of tasks that need completing in the space, some of these need planning or additional materials so before doing these please discuss them on here or in telegram with the infrastructure teams. It maybe beneficial to create a new forum topic to discuss the task’s in greater detail.

These tasks will also be added to Trello where you should move something to complete once its done so we can easily see what’s still left to do.

If you wish to volunteer to do any of these drop an email to board@hacman.org.uk with the tasks your willing to do and when you would do them so we can arrange for your fob to be activated for those times


Updates:
20/06/2021 - @6275marcus


General Space

Misc.
Declutter Nov 20 On-going
Organise waist for Tip / Skip Nov 20 On-going
Empty the cave Nov 20 Completed
Fix Fire Doors around the space Nov 20
Structure
Take down Greenroom ceiling Nov 20 Completed
Take down Greenroom wall Nov 20 Completed
Install new Members Storage shelving Jun 21 Completed
Fix Greenroom toilet & sink area Jun 21
Fill holes in brickwork Jun 21
Fill cracks / holes in floor Jun 21 Completed
Painting
Ceiling Nov 20
Floor Nov 20
Walls Nov 20
Doors
Align correctly Jun 21
Add correct furniture Jun 21
Add access control Jun 21

Metalwork

Structure
Finish plasterboarding Nov 20 Completed
Remove insulation by lift lobby Nov 20 Completed
Fill gaps in breeze block walls Nov 20
Fill cracks / holes in floor Nov 20 Completed
Welding Extraction Nov 20
Move welding room wall Jun 21
Painting
Ceiling Nov 20 Completed
Floor Nov 20 Completed
Walls Nov 20
Doors
Align correctly Nov 20
Add correct furniture Nov 20
Add access control Nov 20
Electrics
Install & wire sockets Nov 20 Work started
Install & wire lighting Nov 20 Work started
Install & wire EM-stop circuit Nov 20

Woodwork

Structure
Fill in plasterboard holes Nov 20 Completed
Replace old fire doors with new single door and breeze blocks Nov 20 Work Started
Finish plasterboarding CNC room Nov 20 Completed
Fill cracks / holes in floor Nov 20
Painting
Ceiling Nov 20
Floor Nov 20
Walls Nov 20
Doors
Align correctly Nov 20
Add correct furniture Nov 20
Add access control Nov 20
Electrics
Install & wire sockets Nov 20 Completed
Install & wire lighting Nov 20 Work started
Install & wire EM-stop circuit Nov 20

Visual Arts

Structure
Build 1/2 height wall Nov 20 Completed
Finish plasterboarding walls Nov 20 Completed
Fix steps Jun 21 Work Started
Build step railing & 1/2 height wall Jun 21
Painting
Ceiling Nov 20
Floor Nov 20
Walls Nov 20

The Cave

Structure
Clean walls Jun 21
Fill holes in brickwork Jun 21
Dig out and fill hole in floor by doorway Jun 21
Build ceiling at far end of room Jun 21
Painting
Ceiling Jun 21
Floor Jun 21
Walls Jun 21
Doors
Align correctly Jun 21
Add correct furniture Jun 21

Network

Structure
Install server rack on wall Nov 20
Install & route cable tray throughout space Nov 20
Network
Setup / Wire Server / Router etc into the Server Rack Nov 20
  • Fit electrical trunking covers

Please do not do this until electrical testing has been completed.

Google Doc containing list of walls we want built using breeze blocks
https://drive.google.com/file/d/1OkIoPLD_6PHWcQY8xWfmZCxcqrkTqnsh/view?usp=sharing

Document will be updated when planning for currently projects is completed / new walls are required

Happy to lend a hand with the wall building. I’m not a pro or even very experienced, but I can do a simple job like brick up a door.

Happy to help with the network things :slight_smile:

I’ll be picking up some stuff for filling in / painting the toilet floor on Sunday (primer for levelling compound, levelling compound, paint)
Although I understand at the moment I need to wait until Monday before I can check if I can get access Monday evening.

For the painting of the ceiling I’d recommend the thicker stuff since it doesn’t drip and covers the walls better. (I think we left a tub of the thinner stuff down there which we gave up on when we painted the cnc room)
I’ll take some pics of the tubs we used the next time I’m down there.

Many Thanks
Richard.

For info for the floor paint in the cnc and metal work rooms, we’ve used Ronseal garage floor paint from b and q. It’s a bit expensive but it’s proper stuff.
We picked some more up recently for when we make a start on the toilet floor area.

Generally it’s also better to do the ceiling first so that white paint is covered up by floor paint, although in this case since the toilet area is quite small we’ll just cover up the floor when we do the ceiling afterwards.

I’ve updated the task list above to reflect what has been completed as well as add new tasks that need completing (along with dates to give some idea of timescale).

Since the space has been open for over two months I think we can resume carrying out major infrastructure tasks once again. Obviously with the current Covid situation please take care and be respectful to other by practicing the Covid measures put in place by the board. As always members should take care to keep disruption to a minimum.

A heads up to the board (board@hacman.org.uk) when you are carrying out any of the task would also be appreciated. Depending on the circumstances and with Board approval, the space may be willing to reimburse any costs expected to carry out work listed above. This would only be approved prior to work being carried out however and subject to the boards discretion.