As you will be aware the space is closed during Lockdown however we have kept it open for anyone wanting to do work on the space as it can be classed as construction site
Below is a list of tasks that need completing in the space, some of these need planning or additional materials so before doing these please discuss them on here or in telegram with the infrastructure teams. It maybe beneficial to create a new forum topic to discuss the task’s in greater detail.
These tasks will also be added to Trello where you should move something to complete once its done so we can easily see what’s still left to do.
If you wish to volunteer to do any of these drop an email to board@hacman.org.uk with the tasks your willing to do and when you would do them so we can arrange for your fob to be activated for those times
Updates:
20/06/2021 - @6275marcus
General Space
Misc.
Declutter
Nov 20
On-going
Organise waist for Tip / Skip
Nov 20
On-going
Empty the cave
Nov 20
Completed
Fix Fire Doors around the space
Nov 20
Structure
Take down Greenroom ceiling
Nov 20
Completed
Take down Greenroom wall
Nov 20
Completed
Install new Members Storage shelving
Jun 21
Completed
Fix Greenroom toilet & sink area
Jun 21
Fill holes in brickwork
Jun 21
Fill cracks / holes in floor
Jun 21
Completed
Painting
Ceiling
Nov 20
Floor
Nov 20
Walls
Nov 20
Doors
Align correctly
Jun 21
Add correct furniture
Jun 21
Add access control
Jun 21
Metalwork
Structure
Finish plasterboarding
Nov 20
Completed
Remove insulation by lift lobby
Nov 20
Completed
Fill gaps in breeze block walls
Nov 20
Fill cracks / holes in floor
Nov 20
Completed
Welding Extraction
Nov 20
Move welding room wall
Jun 21
Painting
Ceiling
Nov 20
Completed
Floor
Nov 20
Completed
Walls
Nov 20
Doors
Align correctly
Nov 20
Add correct furniture
Nov 20
Add access control
Nov 20
Electrics
Install & wire sockets
Nov 20
Work started
Install & wire lighting
Nov 20
Work started
Install & wire EM-stop circuit
Nov 20
Woodwork
Structure
Fill in plasterboard holes
Nov 20
Completed
Replace old fire doors with new single door and breeze blocks
Nov 20
Work Started
Finish plasterboarding CNC room
Nov 20
Completed
Fill cracks / holes in floor
Nov 20
Painting
Ceiling
Nov 20
Floor
Nov 20
Walls
Nov 20
Doors
Align correctly
Nov 20
Add correct furniture
Nov 20
Add access control
Nov 20
Electrics
Install & wire sockets
Nov 20
Completed
Install & wire lighting
Nov 20
Work started
Install & wire EM-stop circuit
Nov 20
Visual Arts
Structure
Build 1/2 height wall
Nov 20
Completed
Finish plasterboarding walls
Nov 20
Completed
Fix steps
Jun 21
Work Started
Build step railing & 1/2 height wall
Jun 21
Painting
Ceiling
Nov 20
Floor
Nov 20
Walls
Nov 20
The Cave
Structure
Clean walls
Jun 21
Fill holes in brickwork
Jun 21
Dig out and fill hole in floor by doorway
Jun 21
Build ceiling at far end of room
Jun 21
Painting
Ceiling
Jun 21
Floor
Jun 21
Walls
Jun 21
Doors
Align correctly
Jun 21
Add correct furniture
Jun 21
Network
Structure
Install server rack on wall
Nov 20
Install & route cable tray throughout space
Nov 20
Network
Setup / Wire Server / Router etc into the Server Rack
I’ll be picking up some stuff for filling in / painting the toilet floor on Sunday (primer for levelling compound, levelling compound, paint)
Although I understand at the moment I need to wait until Monday before I can check if I can get access Monday evening.
For the painting of the ceiling I’d recommend the thicker stuff since it doesn’t drip and covers the walls better. (I think we left a tub of the thinner stuff down there which we gave up on when we painted the cnc room)
I’ll take some pics of the tubs we used the next time I’m down there.
For info for the floor paint in the cnc and metal work rooms, we’ve used Ronseal garage floor paint from b and q. It’s a bit expensive but it’s proper stuff.
We picked some more up recently for when we make a start on the toilet floor area.
Generally it’s also better to do the ceiling first so that white paint is covered up by floor paint, although in this case since the toilet area is quite small we’ll just cover up the floor when we do the ceiling afterwards.
I’ve updated the task list above to reflect what has been completed as well as add new tasks that need completing (along with dates to give some idea of timescale).
Since the space has been open for over two months I think we can resume carrying out major infrastructure tasks once again. Obviously with the current Covid situation please take care and be respectful to other by practicing the Covid measures put in place by the board. As always members should take care to keep disruption to a minimum.
A heads up to the board (board@hacman.org.uk) when you are carrying out any of the task would also be appreciated. Depending on the circumstances and with Board approval, the space may be willing to reimburse any costs expected to carry out work listed above. This would only be approved prior to work being carried out however and subject to the boards discretion.